Home  /  Services capping

Services capping on the Sunshine Coast

Electrical, data, plumbing, gas and refrigeration made safe by licensed trades before demolition starts. The step a cheap quote skips and an inspection catches.

Nothing gets pulled out live

Every commercial fitout is wired and plumbed. Before a single partition comes down, the services running to and through it have to be identified, isolated and capped by the trade licensed to do it. That is a safety requirement, a legal one, and a practical one: a demolition crew that hits a live circuit or a charged water line stops work for the day at best.

Services capping is its own line on a proper quote, done by named licensed trades. If a quote does not mention it, the contractor is either doing it unlicensed or not doing it at all.

Ask who is capping the electrical. If the answer is "we handle it", ask for the licence number.
Close detail of capped services at a commercial wall showing capped copper water pipes, a sealed waste outlet, an electrical junction box with a blank cover plate and tagged data cabling
Capped, blanked, tagged. Each one certified by the trade that did it

By service

Electrical

A licensed electrician isolates tenant circuits at the sub-board, removes tenant wiring back to base building or to an agreed point, blanks outlets and junction boxes, and issues the certificate of testing and safety. Feature lighting circuits, three-phase drops, server room supply and kitchenette power are all in scope. The base building lighting and power stay and are left working.

Data and communications

Structured cabling, patch panels, comms racks and the cabling above the ceiling are tenant fitout. A registered cabler removes them, or caps and labels them if the landlord wants them left. Abandoned cabling from previous tenants is often in the void too, and the lease may make it the current tenant's problem.

Plumbing

A licensed plumber isolates water at the tenancy valve, caps hot and cold at each point, seals wastes, and deals with floor drains, grease traps and any tenant-installed hot water unit. Certified on completion.

Gas

A licensed gas fitter disconnects appliances, isolates and caps at the meter or tenancy boundary, and certifies. Gas is never left live to a capped-off kitchen.

Refrigeration and air conditioning

Tenant-installed split systems, cool rooms and bar refrigeration are degassed by a licensed refrigeration technician before removal. Base building air conditioning stays and is left operating.

Fire services

Sprinklers, detectors, exit lights and extinguishers are base building and stay. Where a partition removal changes coverage, the fire contractor may need to reconfigure, and that is agreed with the landlord.

Certification

Each trade certifies its own work. Those certificates go into the handover pack with the photographs, because the property manager and the incoming tenant's builder will want to know what state the services were left in. A defit without service certificates is a defit with a question mark over it.

Sequencing

Capping happens first, before demolition, and reinstatement of any base building services happens last, after the make good. Trades booked in the wrong order cost days. On a hospitality tenancy with four trades, the sequencing is the whole program.

Written September 2026

Check your lease and the current law before you rely on this

This page describes Queensland commercial lease obligations and defit practice in general terms as they stood in September 2026. The law changes, leases differ, and what applies to you is in your lease.

The statutory position is in the Property Law Act 2023 and, for retail premises, the Retail Shop Leases Act 1994, both at legislation.qld.gov.au. The Queensland Small Business Commissioner publishes a make-good factsheet and offers mediation. Business Queensland covers ending a lease. Building work licensing sits with the Queensland Building and Construction Commission. Where anything here differs from those sources or from your lease, they are right and we are not.

We are not lawyers, property managers or certifiers. For what your lease requires and whether it can be negotiated, get legal advice.

Accurate at the time of writing, September 2026. Always check the source before relying on it.

Questions

Common questions

Why does capping need licensed trades?

Because electrical, plumbing, gas and refrigeration work is licensed work under Queensland law, and because pulling out live services is dangerous. Each trade isolates, caps and certifies its own.

Is capping included in a defit quote?

It should be, as a named item with the trades identified. If a quote does not mention it, ask who is doing it and for their licence number.

What happens to data cabling?

Removed by a registered cabler, or capped and labelled if the landlord wants it left. Abandoned cabling from previous tenants is often in the ceiling void and the lease may make it your problem.

Does base building lighting come out?

No. Base building lighting and power stay and are left working. Only tenant circuits are removed.

Who handles the split system aircon?

A licensed refrigeration technician degasses it before removal. Base building air conditioning stays.

Does the gas have to be capped at the meter?

Isolated and capped at the meter or the tenancy boundary by a licensed gas fitter, and certified. Gas is never left live to a stripped kitchen.

What certificates should I get?

A certificate from each trade for its own work: electrical safety certificate, plumbing compliance, gas compliance, refrigerant handling. They go in the handover pack.

What about the fire sprinklers?

Base building, they stay. If removing partitions changes sprinkler or detector coverage, the fire contractor may need to reconfigure, agreed with the landlord.

Next step

Send the tenancy and the date

Address, rough size, what is in there, and when the lease ends. That is usually enough for a price without anyone visiting.

Scroll to Top