What a make good costs on the Sunshine Coast

What moves the price, why the lease sets it more than the floor area does, and what a quote should itemise so two can actually be compared.

Why there is no price on this page

A 150 square metre office with two partitions and a kitchenette, on a lease that says "remove fitout and make good damage", is a few days and a modest bill. The same 150 square metres as a cafe, on a lease that says "return to cold shell", is two weeks, four licensed trades, a roof penetration and a grease trap. Floor area tells you almost nothing. The lease and the fitout tell you everything.

So the useful thing is knowing what moves the number, because with the lease clause and a description of what is in there, a realistic range is usually possible before anyone visits.

The lease sets the price. The tenancy just sets the multiplier.

The factors, roughly in order

1. What the lease requires

Remove fitout and make good damage, return to original condition, or return to cold shell. Three different jobs at three different prices. This is the biggest variable and it is not chosen by you.

2. Fitout density and type

Open plan office: light. Cellular office with many rooms: medium. Retail with feature walls and tiled floors: heavy. Hospitality or medical with services in every room: heaviest.

3. Services

Each capped point needs a licensed trade. Kitchens, bathrooms, server rooms and treatment rooms multiply this quickly.

4. Floor finish

Carpet tiles lift. Glued vinyl and tiles grind. Adhesive removal is where floor cost lives.

5. Make-good repairs

Patching and painting to a lease standard, ceiling tile replacement, and where required, new carpet. The item cheap quotes omit.

6. Access

Ground floor with a dock: easy. Upper level strata with lift bookings and after-hours rules: slower. Shopping centre with induction, permits and hoarding: slower and dearer again.

7. Waste

Weight-based tipping fees, reduced by sorting and recycling. Asbestos, if present, changes the job entirely.

8. Timeline

A defit with ten weeks runs at normal pace. One with three weeks runs on overtime and weekend rates.

Clipboard with a condition report and a tablet showing photographs on a windowsill in an empty office
The condition report is the cheapest cost control there is. It defines the finish line

What a quote should itemise

  • The make-good standard it is pricing to, in the lease's own words
  • Services capping, by trade, named
  • Joinery and loose fitout removal
  • Partitions and ceilings, with what stays
  • Floor coverings, removal and adhesive, or left in place
  • Make-good repairs: patching, painting, ceiling tiles, skirting, and to what standard
  • Reinstatement items the lease requires, such as new carpet or base building lighting
  • Signage removal and fascia make good
  • Waste, and how it is priced
  • Access costs: induction, permits, hoarding, after hours
  • Builders clean and photographic record
  • Exclusions, stated plainly, especially asbestos

Reading a cheap quote

The usual explanations, none of them dishonest, all of them making comparison meaningless:

  • Strip out only, no make-good repairs
  • Services "made safe" without licensed capping or certificates
  • Floors left in place when the lease requires them out
  • Painting as touch-up rather than full walls
  • Waste by skip with no sorting, priced low and then extra skips billed
  • Daytime rates quoted for a building that only allows after-hours work

The cash settlement alternative

Some landlords will accept a payment instead of the works, particularly where the next tenant will refit anyway. The number that negotiation happens around is a contractor's itemised quote. So a quote has value even if the work is never done. Get it early enough to use it.

Getting a phone estimate

  1. The make-good clause, read out or pasted
  2. Tenancy type and rough floor area
  3. What is in there: rooms, kitchenette, services, floor type
  4. Building type: strata, centre, strip, industrial
  5. Whether a condition report exists
  6. The lease end date
Written September 2026

Check your lease and the current law before you rely on this

This page describes Queensland commercial lease obligations and defit practice in general terms as they stood in September 2026. The law changes, leases differ, and what applies to you is in your lease.

The statutory position is in the Property Law Act 2023 and, for retail premises, the Retail Shop Leases Act 1994, both at legislation.qld.gov.au. The Queensland Small Business Commissioner publishes a make-good factsheet and offers mediation. Business Queensland covers ending a lease. Building work licensing sits with the Queensland Building and Construction Commission. Where anything here differs from those sources or from your lease, they are right and we are not.

We are not lawyers, property managers or certifiers. For what your lease requires and whether it can be negotiated, get legal advice.

Accurate at the time of writing, September 2026. Always check the source before relying on it.

Questions

Common questions

Can I get a price without a site visit?

Often a realistic range, if you can describe the lease clause, the tenancy and what is in it. An unusual building or an unclear lease may need a look.

Why do quotes vary so much?

Scope. Strip out versus strip out plus make good is the biggest gap, then services capping, floors, and painting standard. Compare what each quote names, not the totals.

Does floor area set the price?

Less than people expect. A small hospitality tenancy on a cold shell lease costs more than a large open plan office on a light make-good clause.

Is a cash settlement cheaper than doing the work?

Sometimes. It depends on what the landlord accepts and what the work would cost. A contractor's itemised quote is the number the negotiation runs on either way.

What does a short timeline cost?

Overtime and weekend rates, and less room to sort waste or sequence trades efficiently. Ten weeks is comfortable. Three weeks is expensive.

Are the make-good repairs included?

Ask specifically. It is the item most often left out of cheap quotes, and the landlord will not accept a strip out as a make good.

What about asbestos?

Usually an exclusion in the quote, priced separately if found. Pre-1990 buildings should be tested before work starts, because it changes the job significantly.

Should I get more than one quote?

Two, priced to the same scope. Send both contractors the lease clause and the same description so the numbers mean something.

Next step

Send the tenancy and the date

Address, rough size, what is in there, and when the lease ends. That is usually enough for a price without anyone visiting.